Overall objective is flood protection on the Zagrebačko prisavlje river basin. Specific objectives were:
For Zagreb Prisavlje river basin the widest range of possible measures were considered. The first step was formulation of alternatives, identification of the entire set of potential measures for risk management of floods – structural and non-structural measures. Optimal variant for flood risks management solution includes: hydrological-hydraulic flood forecasting system; equipping several retentions for remote control; rehabilitation and reconstruction of several retentions; construction of flood relief channel; rehabilitation, reconstruction and construction of embankments, walls. Total value of the proposed investment was 161,881,172 kn (21,584,156 €). |